How Long Will My Remodel Project Take in Colorado?

  • Writer: Tanner Thomas
    Tanner Thomas
  • Feb 24
  • 3 min read


Detailed Breakdown of Project Schedules for Remodels


Stage 1 - Design & Pre-Construction Phase: 3-10 Weeks

At Emory Construction, we believe the design, pre-construction, and selection phase is one of the most critical steps in any remodeling project. Taking the time to eliminate potential issues upfront ensures a smoother project with fewer surprises.

We don’t rush into construction without finalizing key selections because it’s nearly impossible to hit a target without first understanding what it looks like, identifying potential challenges, and defining costs.


Example Timelines for This Phase:

(Note: These are just examples. Your project may vary.)

  • Small Project: 4 weeks

  • Medium Project: 6 weeks

  • Large Project: 10 weeks


Factors That Affect This Phase’s Timeline:

  • Permitting

  • Project size & complexity

  • Scope of work

  • Material selection & availability

  • Budget

  • Decision-making delays (materials, finishes, design changes, etc.)


Tips for Speeding Up This Process:

Define Your Style: 

Before hiring a general contractor, collect images and ideas of the design styles you love. At Emory Construction, we specialize in guiding customers through the design process.


Think About Functionality: 

What’s your main goal for this remodel? More space? Improved functionality? A better layout for entertaining? Write down your top priorities and rank them in order of importance.


Create a Scope of Work: 

A clear scope of work helps your contractor understand your vision and uncover any overlooked details that might impact the project.


Set a Realistic Budget: 

Establish a realistic budget, including a 10-20% contingency fund. Even with expert planning, remodels can uncover hidden issues—such as damaged framing, structural concerns, or outdated electrical work. Having extra funds set aside ensures unexpected issues won’t derail your project.


Plan for the Future: 

If you’re opening up walls or updating infrastructure, consider future needs like EV chargers, smart home wiring, or solar panel integration. Thinking ahead can save time and money down the road.


Prioritize Energy Efficiency: 

If replacing windows, doors, or insulation, consider energy-efficient upgrades that lower your utility costs and improve home comfort.



Stage 2 - Initial Construction Phase: 2-6 Weeks

This phase includes demolition, framing, mechanical systems (plumbing, electrical, HVAC), and insulation. It is crucial because it sets the foundation for success and is when most city inspections occur.

At Emory Construction, we have strict quality control measures to ensure that everything is built to code before we move into the finishing stages.


Example Timelines for This Phase:

(Note: These are just examples. Your project may vary.)

  • Small Project: 2-4 weeks

  • Medium Project: 3-5 weeks

  • Large Project: 4-6 weeks



Stage 3 - Finishing Phase: 6-12 Weeks

At this stage, your home starts coming together. Drywall, flooring, cabinets, paint, countertops, and fixtures are installed.

At Emory, we work with top-tier tradespeople to ensure a flawless finish, and each week, you’ll see your home transform before your eyes.


Example Timelines for This Phase:

(Note: These are just examples. Your project may vary.)

  • Small Project: 5-6 weeks

  • Medium Project: 7-9 weeks

  • Large Project: 10-12 weeks



Stage 4 - Punch List & Close-Out Phase: 2-6+ Weeks

The punch list phase ensures all remaining details are completed to perfection. We walk through the home, create a detailed list of final touch-ups, and ensure everything meets our high standards before the final handoff.


💡 Honest Insight: This phase can sometimes be frustrating for homeowners due to delays in materials, specialty orders, or minor adjustments. We understand this and always go the extra mile to ensure you are completely satisfied.


At Emory Construction, we’re not done until you’re happy. If any issues arise after the walkthrough, we take care of them.


Example Timelines for This Phase:

(Note: These are just examples. Your project may vary.)

  • Small Project: 2-4 weeks

  • Medium Project: 3-5 weeks

  • Large Project: 4-6 weeks



Stage 5 - Final Sign-Off & Warranty

Once the punch list is completed, we move into the warranty phase.

While major issues are rare, occasional material defects or appliance malfunctions can happen. If anything arises, just give us a call—we’re happy to take care of you.



Project Timeline Recap:


Small Project Timeline: 12-18 Weeks

Design & Pre-Construction: 4 weeks

Initial Construction: 2-4 weeks

Finishing Stage: 5-6 weeks

Punch List & Close-Out: 2-4 weeks


Medium Project Timeline: 19-25 Weeks

Design & Pre-Construction: 6 weeks

Initial Construction: 3-5 weeks

Finishing Stage: 7-9 weeks

Punch List & Close-Out: 3-5 weeks

Large Project Timeline: 24-34 Weeks

Design & Pre-Construction: 10 weeks

Initial Construction: 4-6 weeks

Finishing Stage: 10-12 weeks

Punch List & Close-Out: 4-6 weeks



Ready to Start Your Remodel?

Click the Contact page in the upper right corner of our website or use the link below to schedule your free consultation with Emory Construction today! 





 
 
 